| Owner Solicitation Name: | Palof Furnace Replacement
|
| Owner Name: | Wisconsin Dept. of Administration, Division of Facilities Development
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Removal of the existing oil fired furnace,
humidifier, A frame air conditioning coil and
oil tank and any existing oil within the tank.
Cap the existing chimney. Replace the existing
furnace, humidifier, filter, thermostat and air
conditioning unit with product as specified
within the specs. The new furnace shall be liquid
petroleum fueled.
|
|
| Owner Solicitation Name: | Furnish and Replace a New Air-Cooled Chiller at City Hall
|
| Owner Name: | Eau Claire Purchasing Dept.
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Furnish and replace a new air-cooled chiller at
city hall.
|
|
| Owner Solicitation Name: | Coalition Water Project
|
| Owner Name: | Dept. of Agriculture, Natural Resources Conservation Service, Wisconsin State Office
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | The technical assistance is to be provided in the
form of small group coalitions. A coalition is a
small group of water system operators or
personnel that live in the same vicinity that
meet informally and periodically to discuss
drinking water topics.
|
|
| Owner Solicitation Name: | 2003 Lost Canyon Regional Detention Facility
|
| Owner Name: | Lake Delton, Village of
|
| Enginner Name: | MSA Professional Services, Inc.
|
| Plankeeper Name |
|
| Scope: | Excavation, grading, and restoration work
associated with the construction of a 20 acre-
foot storm water detention facility, including
ditches, storm sewer, pavement patching, and
associated appurtenances. The work includes
approximately 60,000 CY of unclassified
excavation and approximately 30,000 CY of rock
excavation.
|
|
| Owner Solicitation Name: | Glass Lab/Sculpture Foundry Relocation
|
| Owner Name: | Wisconsin Dept. of Administration, Division of Facilities Development
|
| Enginner Name: | State Division's Plan Distribution Unit
|
| Plankeeper Name |
|
| Scope: | Relocating the Glass Lab and Sculpture Foundry
into existing space in the University Warehouse.
Existing facilities at two locations will be
demolished. Work includes metal stud and drywall
walls, concrete block partitions, vinyl
composition tile, acoustical tile ceilings,
precast concrete mezzanine, concrete work, steel
framing, and overhead coiling doors. Associated
Plumbing, HVAC, Electrical and telecommunications
are also included.
|
|
| Owner Solicitation Name: | Glass Lab/Sculpture Foundry Relocation, Asbestos Abatement
|
| Owner Name: | Wisconsin Dept. of Administration, Division of Facilities Development
|
| Enginner Name: | State Division's Plan Distribution Unit
|
| Plankeeper Name |
|
| Scope: | Removal of asbestos containing transite board,
pipe fitting insulation and flexible duct
connectors, and related work.
|
|
| Owner Solicitation Name: | 2004 Roof Rehabilitation at Madison Metropolitan District
|
| Owner Name: | Madison Metropolitan School District, Building Services Dept.
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Roof rehabilitation.
|
|
| Owner Solicitation Name: | Central Plant Repairs, Demo Existing Softener System and Replace
|
| Owner Name: | Wisconsin Dept. of Administration, Division of Facilities Development
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Complete removal of he existing boiler make up
water softener and dealkalizer system, and
complete replacement of said system with a
softener and reverse osmosis system as specified
here in and on the referenced drawings. The bid
shall include all labor, materials and equipment
required for the complete execution of work scope.
|
|
| Owner Solicitation Name: | Truck, Step Van with Aerial Lift
|
| Owner Name: | Milwaukee Procurement Services Section
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Truck, step van with aerial lift.
|
|
| Owner Solicitation Name: | Revisions to Water Transmission Mains - Myrick Park
|
| Owner Name: | La Crosse, City of, Dept. of Public Works
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Excavation, installation of piping, fittings and
valves, tie in to existing transmission mains.
20 LF 20" piping, 1 hydrant.
|
|
| Owner Solicitation Name: | Rehabilitation of 3 Municipal Wells
|
| Owner Name: | La Crosse, City of, Dept. of Public Works
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Well pump equipment, removal and replacement air
bursting well screens electrical modifications
and additions start-up and training.
|
|
| Owner Solicitation Name: | Electrical Renovations-Wausau Parking Structures
|
| Owner Name: | Wausau, City of
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Electrical renovations.
|
|
| Owner Solicitation Name: | Water and Sewer Lines Reconstruction
|
| Owner Name: | Ripon Public Works Dept.
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | 6,600 LF PVC sewer in a variety of sizes 24 pre-
cast manholes, 95 sanitary laterals and clean
outs, 2,500 CY rock excavation traffic control,
erosion control, pumping water main for alliant
energy installation only of: 6,800 LF of 10" PVC
600 LF of 12" PVC 1,100 LF of 6"-8" PVC 104
service connections and boxes 21 valves 10"-12"
30 valves 6"-8" 16 fire hydrants.
|
|
| Owner Solicitation Name: | Industrial Park Improvements
|
| Owner Name: | Winneconne, Village of
|
| Enginner Name: | MSA Professional Services, Inc.
|
| Plankeeper Name |
|
| Scope: | Open cut 550 LF of 8 diameter PVC sanitary
sewer; 1,750
LF of 8 and 10 diameter PVC water main;
miscellaneous utility construction, clean-up and
all related work.
|
|
| Owner Solicitation Name: | Elevated Water Storage Tank Improvements
|
| Owner Name: | Almena, Village of
|
| Enginner Name: | Cooper Engineering Co., Inc.
|
| Plankeeper Name |
|
| Scope: | Elevated water storage tank improvements.
|
|
| Owner Solicitation Name: | Operation and Maintenance, Rock Paint and Chemical Remediation Site
|
| Owner Name: | Dept. of Agriculture, Natural Resources Conservation Service, Wisconsin State Office
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Operation and maintenance, rock paint and
chemical remediation site.
|
|
| Owner Solicitation Name: | Metro Interceptor Sewer System Menomonee Special W Rebid
|
| Owner Name: | Milwaukee Metropolitan Sewerage District (MMSD)
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Metro Interceptor Sewer System
|
|
| Owner Solicitation Name: | Equipment for the Headworks Upgrade
|
| Owner Name: | Lakeland Sanitary Dist.1
|
| Enginner Name: | Becher-Hoppe Associates, Inc.
|
| Plankeeper Name |
|
| Scope: | Grit removal equipment, fine screen equipment.
|
|
| Owner Solicitation Name: | Onalaska Clinic Expansion
|
| Owner Name: |
|
| Enginner Name: | HSR Associates, Inc.
|
| Plankeeper Name |
|
| Scope: | Clinic expansion, 135,000 SF.
|
|
| Owner Solicitation Name: | Air Conditioning Office/Classroom
|
| Owner Name: | Wisconsin Dept. of Administration, Division of Facilities Development
|
| Enginner Name: | State Division's Plan Distribution Unit
|
| Plankeeper Name |
|
| Scope: | Air conditioning equipment replacement that
includes installation of split systems with
outside air provisions, plus related demolition,
electrical work, replacement of suspended
acoustical ceiling systems to accommodate ceiling
evaporator units, and replacement of exhaust fans.
|
|
| Owner Solicitation Name: | Briarwood Sanitary Sewer Extensions, Lift Station and Force Main
|
| Owner Name: | Franklin, City of
|
| Enginner Name: | Graef Anhalt Schloemer & Associates, Inc.
|
| Plankeeper Name |
|
| Scope: | Open cut 1,147 LF of 15" PVC sanitary sewer,
7,580 LF of 8" PVC sanitary sewer, 2,840 LF of
6" PVC force main, 1 EA of two submersible pump
lift station with control panel, valve vault and
meter manhole, 25,360 SY of asphaltic concrete
pavement, Related manholes, services, site work,
and restoration.
|
|
| Owner Solicitation Name: | Water Tower E Addition
|
| Owner Name: | Fitchburg, City of
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Construction of a new 750,000 gallon, single
pedestal, elevated water storage spheroid tank.
Installation of sitework improvements,
underground piping, and miscellaneous work
required to accomplish the tank addition.
|
|
| Owner Solicitation Name: | Demolition of Buildings
|
| Owner Name: | Eau Claire Purchasing Dept.
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Demolition of buildings.
|
|
| Owner Solicitation Name: | Repair and Re-Laminate 22 Portable Bars
|
| Owner Name: | Madison, City of
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Repair and re-laminate 22 portable bars.
|
|
| Owner Solicitation Name: | Utility Extension
|
| Owner Name: | Grantsburg, Village of
|
| Enginner Name: | Short Elliott Hendrickson, Inc.
|
| Plankeeper Name |
|
| Scope: | 240 LF 8" DI water main, 65 LF 1" copper
service, 1 EA hydrant, 230 LF 8" sanitary sewer,
50 LF 4" sanitary service pipe, 1,100 SY turf
establishment.
|
|
| Owner Solicitation Name: | Infrastructure Management Plan and Water Master Planning Update
|
| Owner Name: | Madison Water Utility
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Consultant services for the completion of an
Infrastructure management plan and the update of
the utility's water master plan.
|
|
| Owner Solicitation Name: | Pre-Cast Concrete Box Culvert
|
| Owner Name: | Dane County, Purchasing Division
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Pre-cast concrete box culvert.
|
|
| Owner Solicitation Name: | Flooring Materials and Installation
|
| Owner Name: | University of Wisconsin-Madison, Purchasing Services
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Flooring materials and installation.
|
|
| Owner Solicitation Name: | Golf Course Revisions to Mee-Kwon Park Golf Course Hole 15 Green and Practice Greens
|
| Owner Name: | Ozaukee County Clerk
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Golf course revisions.
|
|
| Owner Solicitation Name: | Pioneer Window/ HVAC Rplc/Lob
|
| Owner Name: | Wisconsin Dept. of Administration, Division of Facilities Development
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Demolition of all exterior glazing for the
building, radiant ceiling tile, mechanical
ductwork with air handling unit and light
fixtures through out building. Installation of
new aluminum frame windows and doors, new VAV
ductwork system with new air handling unit, new
acoustical ceiling tiles and lighting systems.
First floor renovation consists of new
vestibules, flooring in selected areas and
demolition of 2 small offices.
|
|
| Owner Solicitation Name: | Maryland Montessori School Parking Lot Reconstruction
|
| Owner Name: | Milwaukee Public Schools, Division of Facilities and Maintenance Services
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | School Parking Lot Reconstruction
|
|
| Owner Solicitation Name: | WSPF Outdoor Exercise
|
| Owner Name: | Wisconsin Dept. of Administration, Division of Facilities Development
|
| Enginner Name: | State Division's Plan Distribution Unit
|
| Plankeeper Name |
|
| Scope: | Earthwork, concrete slabs, security fencing, and
hardware for construction of 43 outdoor
recreation areas totaling approximately 27,500
SF. Winter construction will be required.
|
|
| Owner Solicitation Name: | Bridge and Approaches
|
| Owner Name: | Wisconsin Dept. of Transportation, Infrastructure Development
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Excavation, base aggregate, bridge work,
concrete, pavement marking, CSP, RCP, pipe
lining, pipe underdrain, fence, signage,
electrical wire lighting, ITS controller cabinet.
Please see attached file for the entire list of
bid items.
|
|
| Owner Solicitation Name: | Belmont - Mineral Point Road, STH 126 - Cottage Inn Road
|
| Owner Name: | Wisconsin Dept. of Transportation, Infrastructure Development
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Excavation, base aggregate, pavement marking,
concrete, asphaltic material, signage.
Please see attached file for the entire list of
bid items.
|
|
| Owner Solicitation Name: | Madison - Waunakee Road, Knutson Drive to Division Street; Madison - Waunakee Road, Yahara River Bridge and Approaches
|
| Owner Name: | Wisconsin Dept. of Transportation, Infrastructure Development
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Excavation, concrete, bridge work, pavement
marking, base aggregate, culvert pipe, CSP, RCP,
asphaltic material, signage, pipe lining,
electrical wire.
Please see attached file for the entire list of
bid items.
|
|
| Owner Solicitation Name: | Intersection Improvements
|
| Owner Name: | Wisconsin Dept. of Transportation, Infrastructure Development
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Excavation, concrete pavement, pavement marking,
RCP, concrete, asphaltic material, trees,
signage, lighting.
Please see attached file for the entire list of
bid items.
|
|
| Owner Solicitation Name: | STH 188 - STH 78 Road, Wisconisn River Ferry Crossing, North Approach Reconstruction; Wisconsin River Crossing, North Shore Ferry Approach
|
| Owner Name: | Wisconsin Dept. of Transportation, Infrastructure Development
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Excavation, base aggregate, pavement marking,
RCP, concrete, asphaltic material, signage,
electrical wire lighting, ITS communication
cable, hauling, camera cables, restroom building
construction, plumbing, heating.
Please see attached file for the entire list of
bid items.
|
|
| Owner Solicitation Name: | LaBelle Street Bridge and Approaches, City of Boscobel, Saunders Creek Bridge
|
| Owner Name: | Wisconsin Dept. of Transportation, Infrastructure Development
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Excavation, bridge work, concrete, RCP, asphaltic
surface.
Please see attached file for the entire list of
bid items.
|
|
| Owner Solicitation Name: | Narrows Valley Road Bridge and Approaches, Town of Washington
|
| Owner Name: | Wisconsin Dept. of Transportation, Infrastructure Development
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Excavation, bridge work, concrete, asphaltic
surface, railing, riprap, signage.
Please see attached file for the entire list of
bid items.
|
|
| Owner Solicitation Name: | Woodland Drive, Village of Waunakee, Aldora Lane - Division Street; Woodland Drive, Village of Waunakee, Aldora Lane - Division Street
|
| Owner Name: | Wisconsin Dept. of Transportation, Infrastructure Development
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Excavation, base aggregate, pavement marking,
culvert pipe, RCP, concrete, asphaltic material,
signage, electrical wire lighting, DI water main,
water main service.
Please see attached file for the entire list of
bid items.
|
|
| Owner Solicitation Name: | Low Road Bridge and Approaches, Town of Middleton
|
| Owner Name: | Wisconsin Dept. of Transportation, Infrastructure Development
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Excavation, bridge work, base aggregate,
concrete, CSP, RCP.
Please see attached file for the entire list of
bid items.
|
|
| Owner Solicitation Name: | Marquette Interchange Traffic Mitigation, 28th Street WB On-Ramp (Ramp Widening)
|
| Owner Name: | Wisconsin Dept. of Transportation, Infrastructure Development
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Excavation, base aggregate, pavement marking,
RCP, concrete, asphaltic material, underdrain
pipe, fence, signage, channel extension module,
directional boring, timber lagging.
Please see attached file for the entire list of
bid items.
|
|
| Owner Solicitation Name: | Marquette Interchange Traffic Mitigation, Becher Street SB On-Ramp, North Avenue NB On-Ramp
|
| Owner Name: | Wisconsin Dept. of Transportation, Infrastructure Development
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Excavation, base aggregate, pavement marking,
RCP, asphaltic material, signage, concrete,
channel extension module, directional bore.
Please see attached file for the entire list of
bid items.
|
|
| Owner Solicitation Name: | Madison to Fond du Lac Road, Thill Road to Townline Road (New Lanes); Madison to Fond du Lac Road, Thill Road to Townline Road (Existing Lanes)
|
| Owner Name: | Wisconsin Dept. of Transportation, Infrastructure Development
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Excavation, base aggregate, bridge work,
concrete, pavement marking, culvert pipe, RCP,
asphaltic material, pile driving, riprap, signage.
Please see attached file for the entire list of
bid items.
|
|
| Owner Solicitation Name: | W. Good Hope Road (CTH PP), Teutonia - North 91st Street
|
| Owner Name: | Wisconsin Dept. of Transportation, Infrastructure Development
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Signage.
Please see attached file for the entire list of
bid items.
|
|
| Owner Solicitation Name: | N. Teutonia Avenue, W. Bradley Road, and N. 43rd Street, Traffic Signal Rehabilitation
|
| Owner Name: | Wisconsin Dept. of Transportation, Infrastructure Development
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Pavement Marking Epoxy - 590 LF, Optically
Programmed Traffic Signal Faces - 4 Each.
|
|
| Owner Solicitation Name: | Hazard Elimination Safety Project, CTH U (76th Street) - Grange Avenue to Morgan Street
|
| Owner Name: | Wisconsin Dept. of Transportation, Infrastructure Development
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Concrete Bases - 14 EA, Poles - 9 EA; Traffic
Signal Standards - 10 EA, Trombone Arms - 9 EA,
Traffic Signal Mounting Hardware - 5 LS, Traffic
Signal Face LED - 41 EA, Pedestrian Signal Face
LED - 23 EA, Pedestrian Push Buttons - 18 EA.
|
|
| Owner Solicitation Name: | Washington Avenue, Intersection of CTH H
|
| Owner Name: | Wisconsin Dept. of Transportation, Infrastructure Development
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Excavation, base aggregate, pavement marking,
RCP, concrete, asphaltic material, signage,
lighting.
Please see attached file for the entire list of
bid items.
|
|
| Owner Solicitation Name: | CTH ZZ - West College Avenue, STH 241 - South 27th Street to STH 38 - South Howell Avenue
|
| Owner Name: | Wisconsin Dept. of Transportation, Infrastructure Development
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Base aggregate, pavement marking, concrete,
signage, conduit extension.
Please see attached file for the entire list of
bid items.
|
|
| Owner Solicitation Name: | South 27th Street (East Roadway) / West Forest Home Avenue, South 27th Street Bridge Over Union Pacific Railroad to West Lincoln Avenue, South 31st St
|
| Owner Name: | Wisconsin Dept. of Transportation, Infrastructure Development
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Excavation, base aggregate, bridge work, pavement
marking, concrete, asphaltic material, painting,
signage.
Please see attached file for the entire list of
bid items.
|
|
| Owner Solicitation Name: | West Beloit Road, Bridge Over Root River
|
| Owner Name: | Wisconsin Dept. of Transportation, Infrastructure Development
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Excavation, base aggregate, concrete, bridge
work, pile driving, pavement marking, CSP,
asphaltic material, railing, signage.
Please see attached file for the entire list of
bid items.
|
|
| Owner Solicitation Name: | Grandville Road, County Line Road to Mequon Road; Grandville Road, Over the Little Menomonee Creek
|
| Owner Name: | Wisconsin Dept. of Transportation, Infrastructure Development
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Excavation, base aggregate, bridge work, pile
driving, pavement marking, culvert pipe, CSP,
concrete, asphaltic material, PE pipe, riprap,
signage.
Please see attached file for the entire list of
bid items.
|
|
| Owner Solicitation Name: | Fond du Lac - East County Line, USH 151 to CTH W
|
| Owner Name: | Wisconsin Dept. of Transportation, Infrastructure Development
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Excavation, base aggregate, pavement marking,
CSP, RCP, concrete, asphaltic material, signage.
Please see attached file for the entire list of
bid items.
|
|
| Owner Solicitation Name: | Kiel Road to East County Line, Marytown Urban Section
|
| Owner Name: | Wisconsin Dept. of Transportation, Infrastructure Development
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Excavation, base aggregate, pavement marking,
RCP, concrete, asphaltic material, signage.
Please see attached file for the entire list of
bid items.
|
|
| Owner Solicitation Name: | City of Algoma, CTH K - Greenfield Avenue; City of Algoma, Ohio Street - Greenfield Avenue
|
| Owner Name: | Wisconsin Dept. of Transportation, Infrastructure Development
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Excavation, base aggregate, pavement marking,
sanitary sewer pipe, water main, HDPE pipe,
service connections, directional drilling, RCP,
concrete, asphaltic material, manhole, trees,
signage, lighting, storm sewer pipe.
Please see attached file for the entire list of
bid items.
|
|
| Owner Solicitation Name: | Mason Street, City of Green Bay, Fox River Bridge
|
| Owner Name: | Wisconsin Dept. of Transportation, Infrastructure Development
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Base aggregate, pavement marking, concrete, pipe
underdrain, asphaltic material, bridge work,
signage.
Please see attached file for the entire list of
bid items.
|
|
| Owner Solicitation Name: | Bridge and Approaches, Town of Montpelier, Scarboro Creek
|
| Owner Name: | Wisconsin Dept. of Transportation, Infrastructure Development
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Bridge work, concrete, pile driving, railing,
riprap.
Please see attached file for the entire list of
bid items.
|
|
| Owner Solicitation Name: | Custer Street, City of Manitowoc, Alverno Road to CTH R
|
| Owner Name: | Wisconsin Dept. of Transportation, Infrastructure Development
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Excavation, base aggregate, pavement marking,
CSP, RCP, concrete, asphaltic material, riprap,
storm sewer.
Please see attached file for the entire list of
bid items.
|
|
| Owner Solicitation Name: | N. Village Limits - N. County Line, Dover Court - .85 Mi. North CTH Z
|
| Owner Name: | Wisconsin Dept. of Transportation, Infrastructure Development
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Excavation, base aggregate, bridge work, pile
driving, pavement marking, concrete, asphaltic
material, railing, riprap, signage.
Please see attached file for the entire list of
bid items.
|
|
| Owner Solicitation Name: | USH 51 / STH 29 Corridor - Wausau, West Arterial Frontage Road, Oriole Lane to CTH NN
|
| Owner Name: | Wisconsin Dept. of Transportation, Infrastructure Development
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Excavation, base aggregate, pavement marking,
CSP, RCP, concrete, asphaltic material, riprap,
signage, lighting, coating.
Please see attached file for the entire list of
bid items.
|
|
| Owner Solicitation Name: | CTH PP - USH 10 Road, Branch Rocky Run Creek Crossing; STH 34 - CTH O, Rudolph Creek Crossing
|
| Owner Name: | Wisconsin Dept. of Transportation, Infrastructure Development
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Excavation, base aggregate, bridge work, pile
driving, pavement marking, RCP, concrete,
asphaltic material, preboring, railing, riprap,
signage.
Please see attached file for the entire list of
bid items.
|
|
| Owner Solicitation Name: | McCleary Bridge North Approach, S. 17th Avenue, Lake Street to Sherman Street
|
| Owner Name: | Wisconsin Dept. of Transportation, Infrastructure Development
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Excavation, base aggregate, pavement marking,
pipe underdrain, RCP, concrete, asphaltic
material, signage, lighting.
Please see attached file for the entire list of
bid items.
|
|
| Owner Solicitation Name: | I-90 / 94 Interchange Bridge Rehabs, B-41-24, 43, 44 Inters I-90 / 94
|
| Owner Name: | Wisconsin Dept. of Transportation, Infrastructure Development
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Bridge work, base aggregate, concrete, pavement
marking, signage, excavation.
Please see attached file for the entire list of
bid items.
|
|
| Owner Solicitation Name: | Weisenbeck Road, Town of Nelson, (Little Bear Creek Bridge and Approaches)
|
| Owner Name: | Wisconsin Dept. of Transportation, Infrastructure Development
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Excavation, base aggregate, bridge work, pile
driving, railing, riprap.
Please see attached file for the entire list of
bid items.
|
|
| Owner Solicitation Name: | STH 16, City of Sparta, Hamlet Avenue - STH 27
|
| Owner Name: | Wisconsin Dept. of Transportation, Infrastructure Development
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Excavation, base aggregate, pavement marking,
culvert pipe, CSP, RCP, concrete, asphaltic
material, signage, electrical wire, water main,
service connections, sanitary sewer, DIP.
Please see attached file for the entire list of
bid items.
|
|
| Owner Solicitation Name: | Menomonie - Eau Claire Road, (EB USH 12 Bridge B-17-55); Menomonie - Eau Claire Road, (EB Wilson Creek Bridge B-17-175)
|
| Owner Name: | Wisconsin Dept. of Transportation, Infrastructure Development
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Excavation, base aggregate, bridge work, pile
driving, concrete, pavement marking, asphaltic
material, welding, riprap, signage, lighting.
Please see attached file for the entire list of
bid items.
|
|
| Owner Solicitation Name: | Eau Claire - Chippewa Falls Road, CTH J and 47th Avenue Intersections; Eau Claire - Chippewa Falls Road, Woodward Avenue Intersection
|
| Owner Name: | Wisconsin Dept. of Transportation, Infrastructure Development
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Excavation, base aggregate, pavement marking,
culvert pipe, RCP, concrete, asphaltic material,
signage, bridge work, luminaire.
Please see attached file for the entire list of
bid items.
|
|
| Owner Solicitation Name: | Cornell - Ladysmith Road, (STH 64 - North County Line)
|
| Owner Name: | Wisconsin Dept. of Transportation, Infrastructure Development
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Excavation, base aggregate, pavement marking,
culvert pipe, CSP, PE pipe, RCP, concrete,
asphaltic material, signage.
Please see attached file for the entire list of
bid items.
|
|
| Owner Solicitation Name: | District 6, Various Highways, Pavement Marking
|
| Owner Name: | Wisconsin Dept. of Transportation, Infrastructure Development
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Pavement Marking Epoxy - 366,421 LF, Pavement
Marking Paint - 6,330,120 LF, Pavement Marking
Railroad Crossings Epoxy - 4 EA, Pavement Marking
Arrows Epoxy - 9 EA, Words Epoxy - 1 EA, Symbols
Epoxy - 3 EA, Island Nose Epoxy - 4 EA, Pavement
Marking Aerial Enforcement Bars Epoxy 24" - 276
LF.
|
|
| Owner Solicitation Name: | District Wide Special Pavement Marking, District 7
|
| Owner Name: | Wisconsin Dept. of Transportation, Infrastructure Development
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Pavement Marking Epoxy - 26,559 LF.
|
|
| Owner Solicitation Name: | STH 77 - USH 2, City of Hurley
|
| Owner Name: | Wisconsin Dept. of Transportation, Infrastructure Development
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Base aggregate, pavement marking, CSP, concrete,
asphaltic material, signage, manhole adjusting.
Please see attached file for the entire list of
bid items.
|
|
| Owner Solicitation Name: | South County Line - USH 8; Culvert Replacement
|
| Owner Name: | Wisconsin Dept. of Transportation, Infrastructure Development
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Base aggregate, pavement marking, RCP, asphaltic
material, grading, concrete, culvert pipe,
landscape restoration.
Please see attached file for the entire list of
bid items.
|
|
| Owner Solicitation Name: | Quaderers Creek Bridge
|
| Owner Name: | Wisconsin Dept. of Transportation, Infrastructure Development
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Excavation, base aggregate, bridge work, pavement
marking, concrete, asphaltic material.
Please see attached file for the entire list of
bid items.
|
|
| Owner Solicitation Name: | STH 70 - Hayward
|
| Owner Name: | Wisconsin Dept. of Transportation, Infrastructure Development
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Excavation, base aggregate, pavement marking,
culvert pipe, CSP, concrete, signage.
Please see attached file for the entire list of
bid items.
|
|
| Owner Solicitation Name: | City of Hayward, Anderson Road - CTH B
|
| Owner Name: | Wisconsin Dept. of Transportation, Infrastructure Development
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Excavation, base aggregate, pavement marking,
culvert pipe, PE pipe, RCP, concrete, asphaltic
material, signage.
Please see attached file for the entire list of
bid items.
|
|
| Owner Solicitation Name: | Architecture Services for the Ferris Huber Center Remodel Project
|
| Owner Name: | Dane County, Purchasing Division
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Architecture services for building remodeling.
|
|
| Owner Solicitation Name: | Repair Taxiway A, Volk Field CRTC, Camp Douglas
|
| Owner Name: | Departments of the Army and Air Force, USPFO for Wisconsin
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Removal and replacement of approximately 42,175
SY of asphalt, 2,650 CY of concrete, replacement
of existing underdrain system and adjustment of
elevations of existing taxiway edge lights.
|
|
| Owner Solicitation Name: | Infrastructure Improvements, Support Services Renovation
|
| Owner Name: | Wisconsin Dept. of Administration, Division of Facilities Development
|
| Enginner Name: | State Division's Plan Distribution Unit
|
| Plankeeper Name |
|
| Scope: | Approximately 43,000 SF remodeling and
approximately 890 SF addition of the existing
food service/food storage/laundry building. This
work will be completed in two phases of
construction as described in the documents. Work
includes new fire sprinkler protection system
throughout, new heating, ventilating and air
conditioning system, new & remodeled plumbing and
electrical/security systems.
|
|
| Owner Solicitation Name: | 1 T Cab - Chassis with Utility Body and a Compact Pick-Up Truck
|
| Owner Name: | Madison Metropolitan Sewerage District
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | 1 T cab - chassis with utility body and a compact
pickup truck.
|
|
| Owner Solicitation Name: | HazMat Response Trailer
|
| Owner Name: | Brown County, Purchasing Dept.
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | HazMat response trailer.
|
|
| Owner Solicitation Name: | Architecture Services for the Ferris Huber Center Remodel Project
|
| Owner Name: | Dane County, Purchasing Division
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Architecture services for building remodeling.
|
|
| Owner Solicitation Name: | Time and Material - Parks Maintenance cont: 1-7
|
| Owner Name: | Milwaukee County Dept. of Public Works, Division of Architectural Engineering & Environmental Services
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Plumbing; HVAC; electrical; well repair, fence
and gates; roofing; painting.
|
|
| Owner Solicitation Name: | ZOO Construction, Contract 1 and 2
|
| Owner Name: | Milwaukee County Dept. of Public Works, Division of Architectural Engineering & Environmental Services
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | ZOO construction, electrical, fences and gates.
|
|
| Owner Solicitation Name: | Courthouse Complex
|
| Owner Name: | Milwaukee County Dept. of Public Works, Division of Architectural Engineering & Environmental Services
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | General construction, plumbing, fire protection,
HVAC, mechanical insulation, electrical,
substantion maintenance, demolition, landscaping,
roofing, glass and glazing, lath and plastering,
acoustical ceilings, carpet and resilient
flooring, painting.
|
|
| Owner Solicitation Name: | Elevator Assessments and Rehabilitation Design Marcus Center For the Performing Arts
|
| Owner Name: | Milwaukee County Dept. of Public Works, Division of Architectural Engineering & Environmental Services
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Elevator assessments and rehabilitation.
|
|
| Owner Solicitation Name: | Water Treatment Plant and Supply Well #5 Rehabilitation
|
| Owner Name: | Delavan, City of
|
| Enginner Name: | Baxter & Woodman, Inc.
|
| Plankeeper Name |
|
| Scope: | Replacement of the aeration tower plastic packing
material; recoating of interior metal surfaces in
the aerator, holding tank, and filter;
replacement of the filtration bed anthracite
media; rehabilitation of the pumping equipment
including equipment removal, inspection,
equipment replacement or rebuilding, equipment
reinstallation, pumping tests, disinfection and
other miscellaneous items of work.
|
|
| Owner Solicitation Name: | Byron Kilbourn School Parking Lot Reconstruction
|
| Owner Name: | Milwaukee Public Schools, Division of Facilities and Maintenance Services
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Parking lot reconstruction.
|
|
| Owner Solicitation Name: | 2003 Utility Project
|
| Owner Name: | Warrens, Village of
|
| Enginner Name: | MSA Professional Services, Inc.
|
| Plankeeper Name |
|
| Scope: | Street and utility improvements including
1,500 LF of 2" HDPE low pressure sewer mains,
1,000 LF of 8" PVC gravity sewer main, 5,000 LF
of 8" DIP water main, Jack & Bore in 1 loction
under railroad approximately 80 LF 16" steel
casing, 5,000 CY of excavation, 12,000 SY of
base course and 7,500 SY of asphalt surface.
|
|
| Owner Solicitation Name: | Lift Station #4 Replacement
|
| Owner Name: | Siren, Village of
|
| Enginner Name: | RREM, A Division of MSA Professional Services Inc.
|
| Plankeeper Name |
|
| Scope: | Construction of a new submersible pump lift
station including a precast wetwell and valve
vault and 2 new pumps.
|
|
| Owner Solicitation Name: | Unheated Metal Frame Storage Building
|
| Owner Name: | Wisconsin Dept. of Administration, Division of Facilities Development
|
| Enginner Name: | State Division's Plan Distribution Unit
|
| Plankeeper Name |
|
| Scope: | Preparation of detailed design information and
construction of a 1-story pre-engineered wood
frame unheated storage building of approximately
6,000 gross SF. The structure will include, but
not limited to, wood frame wall and roof systems;
metal panel siding and roof systems; cast-in-
place concrete foundation and floor slabs; a
mezzanine 20x25; a well with a yard hydrant;
overhead doors and electrical work. Sitework
includes, but not limited to, earthwork grading
and fill, bituminous paving, and related
improvements. Work also includes professional
supervision of the work in accordance with
Department of Commerce requirements.
|
|
| Owner Solicitation Name: | Four Building Exterior Door Replacement
|
| Owner Name: | Wisconsin Dept. of Administration, Division of Facilities Development
|
| Enginner Name: | State Division's Plan Distribution Unit
|
| Plankeeper Name |
|
| Scope: | Replacement of various exterior and interior
aluminum, hollow metal, wood and brass-clad wood
doors, and some frames, in 4 academic buildings.
|
|
| Owner Solicitation Name: | Sewer Jet, Trailer Mounted
|
| Owner Name: | Milwaukee Procurement Services Section
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Sewer jet, trailer mounted.
|
|
| Owner Solicitation Name: | Truck Chassis, Sewer Rodder
|
| Owner Name: | Milwaukee Procurement Services Section
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Truck chassis, 20,000 Lb. GVW, sewer rodder,
truck mounted.
|
|
| Owner Solicitation Name: | Test Boring and Test Well Drilling
|
| Owner Name: | Bristol, Town of
|
| Enginner Name: | Strand Associates, Inc.
|
| Plankeeper Name |
|
| Scope: | Construction of up to 2 test borings, 2 test
wells, and 4 monitoring wells intended to locate
a site for a municipal water well.
|
|
| Owner Solicitation Name: | Kewaunee Dredging Project
|
| Owner Name: | Kewaunee, City of
|
| Enginner Name: | Ayres Associates
|
| Plankeeper Name |
|
| Scope: | Mechanical or hydraulic dredging approximately
13,000 CY of material that has accumulated in the
marina area of the Kewaunee River.
|
|
| Owner Solicitation Name: | Construction of the Menomonee Special, West
|
| Owner Name: | Milwaukee Metropolitan Sewerage District (MMSD)
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Installation of approximately 6,450 LF of 84"
diameter sewer. Approximately 4,240 LF will
be installed by tunnel construction,
approximately 1,710 LF will be installed by open
cut construction, and approximately 500 LF will
be installed by either tunnel construction or
open cut construction. Installation of
approximately 130 LF of 60" diameter sewer by
open cut construction. Installation of
approximately 100 LF of 42" diameter sewer by
open cut construction. Installation of
approximately 1,230 LF of 24" diameter sewer
from Junction Chamber #3 to the existing siphon
chamber. Approximately 160 LF will be installed
by jack and bore construction. Installation of a
new manhole and approximately 75 LF of 15"
diameter sewer by open cut construction.
Installation of approximately 1,040 LF of 12"
diameter PVC sewer inside an existing 60"
brick MIS including cleaning, inspecting,
disposal of sediment and grouting of the annular
space. Clean, televise, dispose of sediment and
provide CIPP structural rehabilitation of
approximately 550 LF of 42" MIS sewer; Clean,
televise, dispose of sediment and structurally
rehabilitate approximately 700 LF of 30"
MIS sewer by pipe reaming and installing 42"
CCFRPMP. Demolish and provide site restoration.
Abandon approximately 6,000 LF of existing 60"
MIS, approximately 1,900 LF of existing
42" x 75" MIS, approximately 55 LF of existing
42" MIS, and approximately 350 LF of existing
21" MIS; Construct a new Intercepting Structure
380 on the existing 96" combined sewer, a new
Manhole #19, and approximately 105 LF of 42"
diameter sewer by open cut construction. Provide
necessary design by Contractors design engineer
for temporary pumping and
temporary excavation support; and
Provide necessary manhole rehabilitation,
utility and sewer lateral reconnections,
connection to existing sewers, required
structure removals and modifications, new cast-
in-place manholes, required drop connections and
bulkheads, surface restoration, geotechnical,
explosive and contaminated soil and water
monitoring, coordination with other contractors,
handling of sewage and water, construction in
poor soils, and all other requirements as
specified and as shown on the plans.
|
|
| Owner Solicitation Name: | Refurbishing of 3rd Floor Courtroom at the Racine County Courthouse
|
| Owner Name: | Racine County, Public Works Dept.
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Refinish, remodel and/or replace antique wood
walls, benches, ceilings, flooring, light
fixtures.
|
|
| Owner Solicitation Name: | Repair and Repaint Interior and/or Exterior Wall and Trim Surfaces at various Racine County Owned Facilities
|
| Owner Name: | Racine County, Public Works Dept.
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Repair and repaint interior and/or exterior wall
and trim surfaces.
|
|
| Owner Solicitation Name: | Removal, Disposal, Purchase and Installation of New Carpeting in Various Racine County Owned Facilities
|
| Owner Name: | Racine County, Public Works Dept.
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Removal and disposal of existing carpeting.
Purchase and installation of new carpeting.
|
|
| Owner Solicitation Name: | Carpet Removal and Installation at Festival Hall
|
| Owner Name: | Racine Public Works Dept.
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Carpet removal and installation.
|
|
| Owner Solicitation Name: | Loader, Tractor, Backhoe
|
| Owner Name: | East Troy, Town of
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Loader, tractor, backhoe.
|
|
| Owner Solicitation Name: | Sanitary Sewer Replacement
|
| Owner Name: | Wittenberg, Village of
|
| Enginner Name: | Foth & Van Dyke & Associates, Inc.
|
| Plankeeper Name |
|
| Scope: | Open cut installation of approximately
2,900 LF 8"-18" PVC sanitary sewer, 900 LF 4" &
6" PVC sewer laterals, 4,000 SY of asphaltic
concrete pavement restoration, 40 SY of concrete
sidewalk restoration.
|
|
| Owner Solicitation Name: | Install Portable Armory, U.S. Coast Guard Group
|
| Owner Name: | DHS - Direct Reports, United States Coast Guard (USCG), Commanding Officer
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Remove approximately 30 SY of asphalt pavement
and excavate approximately 16 CY of material to
allow for installation of new concrete foundation
for portable armory. Install 36 LF of new
reinforced 2' by 2' footer and 8 " foundation
wall and 264 SF reinforced concrete slab, 6"
thick. Remove approximately 35 SY of asphalt
pavement and excavate approximately 200 LF of 1',
6" wide by 2', 6" deep trench for new conduit.
Install approximately 200 LF of new 2" diameter
rigid metal conduit, 220 LF of new 4" diameter
PVC conduit and all wiring, breakers and
accessories for electrical applications as
detailed on drawings. Install approximately 225
LF of new 4" diameter rigid metal conduit and 220
LF of new 4' diameter PVC conduit for
communication applications as detailed.
|
|
| Owner Solicitation Name: | UWEC Towers Hall Fire Sprinkler System
|
| Owner Name: | Wisconsin Dept. of Administration, Division of Facilities Development
|
| Enginner Name: | State Division's Plan Distribution Unit
|
| Plankeeper Name |
|
| Scope: | Installation of fire protection sprinkler system,
including preparation and repair of existing
surfaces, installation of manufactured soffits,
construction of generator enclosure, installation
of emergency generator, alterations and additions
to electrical service, in two high-rise dormitory
towers.
|
|
| Owner Solicitation Name: | Harbor Siphons
|
| Owner Name: | Milwaukee Metropolitan Sewerage District (MMSD)
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Approximately 6,000 LF of 3-barrel siphon sewer
constructed in a single bedrock tunnel containing
2 72" diameter conduits and 1 78" diameter
conduit; approximately 3,500 LF of 3-barrel
siphon sewer constructed in a single bedrock
tunnel containing 2 48" diameter conduits
and one 78" diameter conduit; approximately 2,500
LF of 2-barrel siphon sewer constructed in a
single bedrock tunnel containing one 48" diameter
conduit and one 72" diameter conduit;
approximately 2,400 LF of 4-barrel siphon sewer
constructed in a single bedrock tunnel containing
one 42" diameter conduit, 1 48" diameter conduit,
one 60" diameter conduit and one 96" diameter
conduit; 3 siphon drop shafts with
depths of 250 to 300 LF; one tunnel junction
chamber; 3 flow splitting structures;
modifications to 2 existing siphon valve
chambers, approximately 325 LF of 42", 48", 72",
84" and 96" diameter piped connections between
the drop shafts and flow splitting structures;
one structure that connects a flow splitting
structure to an existing 60" diameter MIS; 1
connection to an existing 84" diameter
Metropolitan Interceptor Sewer (MIS); 1 riser
shaft approximately 300 LF deep, 3 access
structures with depths of 250 to 300
LF; 2 flow control chambers at the Jones Island
Wastewater Treatment Plant (JIWWTP);
approximately 125 LF of 96" diameter pipe
connecting to an existing 72" diameter influent
pipe at the JIWWTP; approximately
185 LF of 90" diameter pipe connecting to an
existing 90" diameter influent pipe at the JIWWTP;
approximately 50 LF of 72" diameter pipe
connecting a flow control chamber to an existing
72" siphon riser shaft; and approximately 50 LF
of 90" diameter pipe connecting to an existing 90-
inch siphon riser shaft. The project contemplated
also includes approximately 520 LF of cellular
cofferdam dock wall with a concrete cap
at the JIWWTP. All structures will be of cast-in-
place construction and several structures and
pipe runs will be on pile foundations.
|
|
| Owner Solicitation Name: | 1 Heavy Duty 1 T Crew Cab Truck with Dump Box, 1 Tandem Axle Plow Truck with Attachments, 1 2.75 Yard Asphalt Patch Trailer, 1 8.5 T Carrydeck Crane
|
| Owner Name: | Douglas County Highway Committee
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | 1 Heavy duty 1 T crew cab truck with dump box, 1
tandem axle plow truck with attachments, 1 2.75
yard asphalt patch trailer, 1 8.5 T carrydeck
crane with 2-man work platform, 1 11-wheel rubber
tired roller.
|
|
| Owner Solicitation Name: | Combined Sewer Relays and Lining
|
| Owner Name: | Milwaukee Public Works Dept.
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Install 22 LF 12" combined sewer, 284 LF 15"
combined sewer, 441 LF 18" combined sewer, 428
LF 21" combined sewer, 158 LF 24" combined
sewer, 184 LF 22x34" combined sewer,
rehabilitate 4 manholes, 483 LF Cured-in-Place
Pipe lining (CIPP), 517 LF 18" CIPP sewer, 207
LF 18" CIPP sewer, 301 LF 22" CIPP sewer.
|
|
| Owner Solicitation Name: | Tree Cutting Services
|
| Owner Name: | Winnebago County, Purchasing Dept.
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Emergency tree removal as well as routine tree
removal in the various County Parks. Cutting down
trees, branches, stumps, and other debris from
the work site.
|
|
| Owner Solicitation Name: | Time and Material Fac. Management - Grounds, Contract 1 - 7
|
| Owner Name: | Milwaukee County Dept. of Public Works, Division of Architectural Engineering & Environmental Services
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | General construction, plumbing, HVAC, electrical,
roofing, carpet and resilient flooring, painting.
|
|
| Owner Solicitation Name: | Combined Sewer Relays
|
| Owner Name: | Milwaukee Public Works Dept.
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | 1,044 LF 15" combined sewer, 307 LF 18" combined
sewer, 860 LF 21" combined sewer, 278 LF 24"
combined sewer.
|
|
| Owner Solicitation Name: | Refrigeration Storage Tanks for the Walnut Street Heating Plant
|
| Owner Name: | University of Wisconsin-Madison, Purchasing Services
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Refrigeration storage tanks.
|
|
| Owner Solicitation Name: | Highway Materials
|
| Owner Name: | Winnebago County, Purchasing Dept.
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Asphalt rubber sealant cold patch material and
crushed stone / gravel, concrete culvert pipe and
materials and guard rail and accessories, hot mix
asphaltic concrete, road oil.
|
|
| Owner Solicitation Name: | CTH F, STH 32 Club House Lane
|
| Owner Name: | Oconto County
|
| Enginner Name: | Ayres Associates
|
| Plankeeper Name |
|
| Scope: | Storm sewer, curb and gutter, beam guard, and
bridge rehabilitation.
|
|
| Owner Solicitation Name: | VC - Cement Masonry Type N
|
| Owner Name: | Milwaukee Procurement Services Section
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | VC - cement masonry type N.
|
|
| Owner Solicitation Name: | Howard Temin Lakeshore Path, Re-Bid
|
| Owner Name: | Wisconsin Dept. of Administration, Division of Facilities Development
|
| Enginner Name: | State Division's Plan Distribution Unit
|
| Plankeeper Name |
|
| Scope: | Reconstruction of approximately 8,900 LF of an
asphalt bike and pedestrian path.
|
|
| Owner Solicitation Name: | Transfer Station and Self-Help Centers Operation
|
| Owner Name: | Milwaukee Public Works Dept.
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Transfer station and self-help centers operation
with associated hauling and disposal services.
|
|
| Owner Solicitation Name: | NWC Boiler Blowdown/Piping Modifications
|
| Owner Name: | Wisconsin Dept. of Administration, Division of Facilities Development
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Boiler blowdown/ piping modifications.
|
|
| Owner Solicitation Name: | Installation of A/C Units at the Ski Lodge
|
| Owner Name: | Brown County, Purchasing Dept.
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Installation of A/C units.
|
|
| Owner Solicitation Name: | Water Main Project (Phase 1)
|
| Owner Name: | Cambria, Village of
|
| Enginner Name: | MSA Professional Services, Inc.
|
| Plankeeper Name |
|
| Scope: | Open cut 1,934 LF 16" Diameter Water Main.
|
|
| Owner Solicitation Name: | Zelazo Rooftop Cooling Units Replace
|
| Owner Name: | Wisconsin Dept. of Administration, Division of Facilities Development
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Removal of two rooftop mounted cooling units and
replacement with new units of similar capacity.
|
|
| Owner Solicitation Name: | Kenwood Avenue Sanitary Sewer Extension
|
| Owner Name: | Beloit Purchasing Division
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Approximately 330 LF 8" PVC sanitary sewer main,
140 LF sanitary sewer laterals, 1 each sanitary
manhole.
|
|
| Owner Solicitation Name: | Jet Fuel Tank Installation
|
| Owner Name: | Waukesha County, Purchasing Division
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Jet fuel tank installation.
|
|
| Owner Solicitation Name: | Concrete Testing Service
|
| Owner Name: | Milwaukee County, Procurement Division
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Concrete testing service.
|
|
| Owner Solicitation Name: | Water Treatment Plan Fence Installation
|
| Owner Name: | Eau Claire Purchasing Dept.
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Water treatment plan fence installation.
|
|
| Owner Solicitation Name: | Engineering Services for the Jones Island Wastewater Treatment Plant Fire Protection System Upgrade
|
| Owner Name: | Milwaukee Metropolitan Sewerage District (MMSD)
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | This project shall include services for the
following tasks: project management, design, bid
and award, engineering services during
construction ESDC, operation and maintenance
(O&M), start-up and training tasks, and
applications engineering (AE).
|
|
| Owner Solicitation Name: | Waterway System Upgrade and Repair
|
| Owner Name: | Wisconsin Dept. of Health and Family Services, Division of State Facilities
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Waterway system upgrade and repair - watershed/
storm water.
|
|
| Owner Solicitation Name: | Grading
|
| Owner Name: | Milwaukee Public Works Dept.
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Grading.
|
|
| Owner Solicitation Name: | Provide Road Centerline Mapping Services
|
| Owner Name: | Eau Claire Purchasing Dept.
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Provide road centerline mapping services.
|
|
| Owner Solicitation Name: | Display Wall Project
|
| Owner Name: | Moraine Park Technical College
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Construction and installation of extruded
aluminum graphic wall sections.
|
|
| Owner Solicitation Name: | Goodman Wetland Restoration Project
|
| Owner Name: | Dept. of Agriculture, Natural Resources Conservation Service, Wisconsin State Office
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Construct a low embankment of approximately 1.5
LF above the existing site grades. Cut off
several shallow surface drains and restore the
wetland hydrology. Work will include
approximately 3016 cy stripping (embankment);
3260 cy stripping (scrapes/borrow); 5016 mineral
fill (embankment); 2021 cy embankment topsoiling;
3260 scrape/borrow topsoiling; 3 AC embankment
seeding; 3.5 AC scrape/borrow areas seeding;
mobilization; and erosion control.
|
|
| Owner Solicitation Name: | Steel Plate Beam Guard
|
| Owner Name: | Dane County, Purchasing Division
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Steel plate beam guard.
|
|
| Owner Solicitation Name: | Slichter Office Level HVAC Replacement
|
| Owner Name: | Wisconsin Dept. of Administration, Division of Facilities Development
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Replace the HVAC units in the lower level office
area.
|
|
| Owner Solicitation Name: | Paulson Road Over Sugar River, Structure B-13-568
|
| Owner Name: | Springdale, Town of
|
| Enginner Name: | MSA Professional Services, Inc.
|
| Plankeeper Name |
|
| Scope: | Grading, base aggregate dense, breaker run,
asphaltic surface, culvert pipe, removal of
existing bridge, and Structure B-13-568.
|
|
| Owner Solicitation Name: | 1 35,000 GVW 5 CY Diesel Dump Truck With Snow Plow and Tailgate Material Spreader
|
| Owner Name: | Racine County, Purchasing Dept.
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | 1 35,000 GVW 5 CY diesel dump truck with snow
plow and tailgate material spreader.
|
|
| Owner Solicitation Name: | Boiler Replacement
|
| Owner Name: | Wisconsin Dept. of Administration, Division of Facilities Development
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Coordination and marking duties for existing
boiler and boiler system demolition work (actual
demolition by asbestos abatement contractor), the
removal of a window and a partial wall to
facilitate demolition work by asbestos abatement
contractor, temporary fuel piping and steam
piping removal work, temporary gas piping supply
to summer boiler, installation of two (2) new 200
HP firetube high pressure steam boilers including
new breeching, feedwater, blowdown, steam, fuel
oil, gas, electrical and control systems to be re-
connected to existing systems. Additional general
work includes rebuilding plant wall,
reinstallation of window, concrete floor infill
remediation work including new concrete boiler
pads.
|
|
| Owner Solicitation Name: | UW Waukesha Electrical Distribution System Replacement
|
| Owner Name: | Waukesha County, Purchasing Division
|
| Enginner Name: | ERS/GMB Engineering Equipment, Inc.
|
| Plankeeper Name |
|
| Scope: | Electrical distribution system replacement.
|
|
| Owner Solicitation Name: | Rice and Whitewater Boat Access, Public Access Site Redevelopment
|
| Owner Name: | Wisconsin Dept. of Administration, Division of Facilities Development
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | In general the work consists of removing the
existing boat ramp, dredging and installing a new
concrete pushed-in-place ramp. The asphalt on the
existing parking area will be removed. The
parking lot will then be graded and re-paved.
Miscellaneous work includes placement of riprap,
construction of a concrete dock interface
station, striping and restoration.
|
|
| Owner Solicitation Name: | Big St. Germain Lake Boat Access - Public Access Site Redevelopment
|
| Owner Name: | Wisconsin Dept. of Administration, Division of Facilities Development
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | In general the work consists of removing the
existing boat ramp, dredging, under water base
preparation, and installing a new concrete boat
ramp. The existing asphalt parking lot will be
pulverized, graded and re-paved. Miscellaneous
work includes placement of riprap, construction
of a concrete dock interface station, clearing
and grubbing, striping and restoration.
|
|
| Owner Solicitation Name: | Inspect, Sample and Test for Asbestos Contining Materials and Design, Bid and Monitor Abatement Projects
|
| Owner Name: | Waukesha County, Purchasing Division
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Inspect, aample and test for asbestos contining
materials and design, bid and monitor abatement
projects.
|
|
| Owner Solicitation Name: | Engineering Services for a Comprehensive Sewer Study
|
| Owner Name: | Superior, City of
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | General and specialized engineering services for
the Wastewater Division of Public Works such as
assisting in the implementation of a computerized
hydraulic/hydrologic modeling program for
performance evaluation of the existing collection
system and for evaluation of potential
alterations to the system; preliminary
engineering (to include characterization of
concerns and quantification of associated
impacts, development and comparative analysis of
alternatives to reduce/eliminate impacts) and
preliminary design; conduct a feasibility study
and preliminary engineering for sewer separation
or partial separation of sewers in combined
districts; identification and analysis of
alternatives for further reduction in
hydraulic/hydrologic demand on sanitary and
combined sewers; analyze alternatives to slow
velocity/flow rate from storm sewers to receiving
waters; investigate options to attenuate wet
weather flow rates to combined/storm sewers;
develop a long term CSO control plan; develop a
Sewer Evaluation and Capacity Assurance Plan
(SECAP); and/or other engineering services as
authorized by the Director of Public Works or his
designee.
|
|
| Owner Solicitation Name: | Public Education and Survey Services For the Comprehensive Study, All Hazard Mitigation Plan, and other Superior Wastewater Treatment Facility Program
|
| Owner Name: | Superior, City of
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Specialized public education and survey services
for the Wastewater Division of Public Works,
including but not limited to preparation,
production, administration, analysis, and
reporting of a telephone and paper-based survey,
plus media consultation and public education
activities.
|
|
| Owner Solicitation Name: | Overhead Garage Doors
|
| Owner Name: | Pilsen, Town of
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | 2 - 14'x12' and 1 16'x13' overhead garage doors.
Tracking, new weathering, remote operators and
labor to remove the old doors and install the new
ones.
|
|
| Owner Solicitation Name: | Health Services Remodeling
|
| Owner Name: | Wisconsin Dept. of Administration, Division of Facilities Development
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Renovation of the existing Health Services Unit
(HSU) which will include remodeling of the nurse
and Officer stations, redesign of the circulation
space, replacement of exterior windows, updating
finishes in the area and other security
modifications. Work will occur on the first floor
of the HSU in an area of approximately 1845 GSF.
|
|
| Owner Solicitation Name: | UWEC Oak Ridge South Electrical Services Upgrade RE-BID
|
| Owner Name: | Wisconsin Dept. of Administration, Division of Facilities Development
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | New 12.47 KV pad-mounted switch, new primary
transformer and new 120/208 volt switchboard.
|
|
| Owner Solicitation Name: | Vehicle, Truck Chassis
|
| Owner Name: | Eau Claire County, Purchasing Dept.
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Vehicle, truck chassis.
|
|
| Owner Solicitation Name: | Rental-Dump Trucks, Landscape Service
|
| Owner Name: | Milwaukee County, Procurement Division
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Rental-dump trucks, landscape service.
|
|
| Owner Solicitation Name: | Crackfilling Contract
|
| Owner Name: | Milwaukee Public Works Dept.
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Crackfilling contract.
|
|
| Owner Solicitation Name: | Sealcoating Contract
|
| Owner Name: | Milwaukee Public Works Dept.
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Sealcoating contract.
|
|
| Owner Solicitation Name: | Architectural Services for a Renovate New ADOL Area #FP03
|
| Owner Name: | Brown County, Purchasing Dept.
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Provide architect and engineering services for
the renovation of a designated section of Unit 7.
|
|
| Owner Solicitation Name: | Architectural Services for a Renovate New ADOL Area #FP03
|
| Owner Name: | Brown County, Purchasing Dept.
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Provide architect and engineering services for
the renovation of a designated section of Unit
7. *See attached file for further details.
|
|
| Owner Solicitation Name: | New or Used 13,000 Lb. Maintainer / Grader
|
| Owner Name: | Ashland Dept. of Public Works
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | New or used 13,000 Lb. maintainer / grader.
|
|
| Owner Solicitation Name: | River Commons Electrical Line
|
| Owner Name: | Wisconsin Dept. of Administration, Division of Facilities Development
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Approximately 1000- feet of 15 kV electrical
feeder cable; new underground ductbank, new
manholes, switchgear and auxiliary equipment.
|
|
| Owner Solicitation Name: | Supplying Clay Materials
|
| Owner Name: | Winnebago County, Purchasing Dept.
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Furnishing, loading, hauling and stockpiling clay
in a designated area of site. The total estimated
clay quantity required is approximately 430,000
compacted in-place CY, 525,000 in-situ CY.
|
|
| Owner Solicitation Name: | Water Treatment Facility - Filter Replacement
|
| Owner Name: | Wisconsin Rapids, City of, Water Works & Lighting Commission
|
| Enginner Name: | Bonestroo, Rosene, Anderlik & Associates, Inc.
|
| Plankeeper Name |
|
| Scope: | Filter Replacement.
|
|
| Owner Solicitation Name: | Ambrose Hall Fascia Replacement
|
| Owner Name: | Wisconsin Dept. of Administration, Division of Facilities Development
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | In general the work consists of removing the
existing fascia system (transite soffit system
removed by others) on both roof levels of the
building. Existing soffit lights and wiring will
be removed. A new metal clad composite panelized
fascia and soffit system with subframing will be
installed in its place. A new coping cap system
and joint sealant will be included as well.
|
|
| Owner Solicitation Name: | Hanger Demolition
|
| Owner Name: | Winnebago County, Purchasing Dept.
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Total demolition of the aircraft hanger and any
other structures designated and the subsequent
removal of all materials and debris from the site.
|
|
| Owner Solicitation Name: | Truck Chassis
|
| Owner Name: | Milwaukee Procurement Services Section
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Truck chassis, 16,500 LB. G.V.W., 4x2, with duct
rodder retrofit.
|
|
| Owner Solicitation Name: | Asphalt Resurfacing
|
| Owner Name: | Milwaukee Public Works Dept.
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Asphalt resurfacing.
|
|
| Owner Solicitation Name: | East Landscape Maintenance of Portions of the Medians on the Eastside of Madison, Sprecher Road, Milwaukee Street, Cottage Grove Road, and Aberg Avenu
|
| Owner Name: | Madison Purchasing Services
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Landscape maintenance services for selected
medians.
|
|
| Owner Solicitation Name: | Central Landscape Maintenance of Portions of the Medians in Central Madison
|
| Owner Name: | Madison Purchasing Services
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Landscape maintenance services for selected
medians.
|
|
| Owner Solicitation Name: | West Landscape Maintenance of Portions of the Medians on the Westside of Madison
|
| Owner Name: | Madison Purchasing Services
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Landscape maintenance services for selected
medians.
|
|
| Owner Solicitation Name: | Wisconsin Avenue Reconstruction, Re-Bid
|
| Owner Name: | Grafton, Village of, Public Works Dept.
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | 1,520 LF 18" to 15" PVC Sanitary Sewer, 31 Each
6" PVC Sanitary Laterals, 5 Each Sanitary
Manhole, 1,550 LF 8" PVC Water Main, 32 Each
Water Services, 200 CY Rock Excavation, 9,025
Sq. Yds. Pavement Removal, 1,850 CY Unclassified
Excavation, 3,570 T Crushed Aggregate Base
Course, 2,010 T Asphaltic Concrete Pavement.
|
|
| Owner Solicitation Name: | 11th Avenue/Bridge Street Roadway and Utility Reconstruction
|
| Owner Name: | Grafton, Village of, Public Works Dept.
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Section 1 - Roadway and Grading -
2,100 CY Common Excavation, 3,000 T Crushed
Aggregate Base Course, 1,000 SY Milling
Pavement, 1,900 T Asphaltic Concrete Pavement,
2,600 LF 30" Curb and Gutter, 11,000 SF 5"
Concrete Sidewalk, 350 SY 7" Concrete Driveway,
6,000 SF 5" Colored and Stamped Concrete,
Section 2 - Storm Sewer, 222 LF 12" HDPE Storm
Sewer, 40 LF 15" HDPE Storm Sewer, 38 LF 18"
HDPE Storm Sewer, 135 LF 24" HDPE Storm, 28 VF
48" Storm Sewer Manhole, 10 Each Catch Basins
Section 3 - Water Main - 846 LF 8" PVC Water
Main Relay, 100 CY Rock Excavation
Section 4 - Sanitary Sewer, 840 LF 15" PVC
Sanitary Sewer Relay, 22 VF 48" Sanitary Manhole.
|
|
| Owner Solicitation Name: | Watermain Construction
|
| Owner Name: | Denmark, Village of
|
| Enginner Name: | Robert E. Lee & Associates
|
| Plankeeper Name |
|
| Scope: | Work includes 5,100 LF of 10" PVC watermain, 500
LF of 8" PVC watermain; and other associated
appurtenances.
|
|
| Owner Solicitation Name: | South St Augustine Street Utility and Street Reconstruction
|
| Owner Name: | Pulaski, Village of
|
| Enginner Name: | Robert E. Lee & Associates
|
| Plankeeper Name |
|
| Scope: | 306 LF of 10" sanitary sewer remove and replace,
2,100 LF of 8" sanitary sewer remove and replace,
72 VF of sanitary manholes, 2,000 LF of 10"
watermain remove and replace, 500 LF of 8"
watermain remove and replace, 420 LF of 24" storm
sewer remove and replace, 660 LF of 18" storm
sewer remove and replace, 600 LF of 12" storm
sewer remove and replace, 55 VF of storm
manholes, 16 each storm inlets, 5,300 T of
pavement removal millings, 17,500 CY of
unclassified excavation, 24,000 SY of base course
material, 24,000 SY of breaker run material,
24,000 SY of asphalt pavement, 4,000 LF of curb
and gutter remove and replace, 5,000 SF of
sidewalk remove and replace.
|
|
| Owner Solicitation Name: | Design and Engineering Services for the Jones Islang Wastewater Treatment Plant Silo Dust Control System Upgrade and Silo Discharge Valve Replacement
|
| Owner Name: | Milwaukee Metropolitan Sewerage District (MMSD)
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Project management, design service, bid and
award, engineering services during construction
(ESDC), operation and maintenance manuals
startup and training, and applications engineering
(AE) to improve the dust control systems.
|
|
| Owner Solicitation Name: | 1 Tri-Axle Truck Chassis
|
| Owner Name: | Winnebago County Highway Commission
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | 1 Tri-axle truck chassis.
|
|
| Owner Solicitation Name: | 2 Tandem Truck Chassis
|
| Owner Name: | Winnebago County Highway Commission
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | 2 tandem truck chassis.
|
|
| Owner Solicitation Name: | Crushed Stone and Gravel
|
| Owner Name: | Dane County, Purchasing Division
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Crushed stone and gravel.
|
|
| Owner Solicitation Name: | Asphaltic Concrete Products
|
| Owner Name: | Dane County, Purchasing Division
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Asphaltic concrete products.
|
|
| Owner Solicitation Name: | Fencing
|
| Owner Name: | Tri-County Recreational Corridor Commission
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Fencing at 2 locations.
|
|
| Owner Solicitation Name: | Randall Street Substation Upgrade
|
| Owner Name: | Wisconsin Dept. of Administration, Division of Facilities Development
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Phase I of the elimination of the existing Street
Substation, reconfiguration of the existing 5kV
distribution tie feeders supplying power to the
Computer Science Building, replacement of
existing 5kV oil switches with a new lineup of 5
kV switchgear a Library, and conversion of the
Psychology Building from 4.16 kV to 13.8kV supply
voltage.
|
|
| Owner Solicitation Name: | Classroom Renovation/Instructional Techn
|
| Owner Name: | Wisconsin Dept. of Administration, Division of Facilities Development
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Renovation of six existing classrooms and a
lecture Hall in four separate buildings. Work
includes metal stud and drywall walls; wood,
vinyl composition tile, carpet flooring,
acoustical tile ceilings, fixed seating and
tables and minor structural work. Plumbing, HVAC,
electrical, telecommunications are also included.
Base Bids will be received as follows: A single
lump sum bid for all work or separate lump sum
bids for: 1) General; 2) Plumbing and Heating,
Ventilating, Air Conditioning; 3) Electrical.
|
|
| Owner Solicitation Name: | Installation of Fencing and Construction and Installation of New Concrete Sidewalks,
|
| Owner Name: | Chesterfield County, Purchasing Dept.
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Furnishing all labor, materials and
equipment to properly construct and complete
galvanized chain link fencing and concrete work.
|
|
| Owner Solicitation Name: | WSPF Outdoor Exercise
|
| Owner Name: | Wisconsin Dept. of Administration, Division of Facilities Development
|
| Enginner Name: | State Division's Plan Distribution Unit
|
| Plankeeper Name |
|
| Scope: | Electrical door monitoring, intercoms and
security cameras for 43 outdoor fenced exercise
areas. Work will require on site mock-ups of
cameras. Construction of the exercise areas has
been previously bid. Winter construction will be
required.
|
|
| Owner Solicitation Name: | CTH T and CTH W Intersection Improvements
|
| Owner Name: | Ozaukee County Clerk
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Common excavation, crushed aggregate base course,
curb and gutter, reinforced concrete storm sewer,
steel plate beam guard, pavement marking,
asphaltic concrete pavement items.
|
|
| Owner Solicitation Name: | Seminole Hills Stormwater Detention Basin, Rebid
|
| Owner Name: | Fitchburg, City of
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Clearing and grubbing; 9,300 CY of excavation,
hauling and disposal; 4,000 SY of seeding and
erosion matting; 90 SY of riprap work; and tree
installation and relocation.
|
|
| Owner Solicitation Name: | Inline Storage System Head Tank Installation
|
| Owner Name: | Milwaukee Metropolitan Sewerage District (MMSD)
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Replacing 2 existing head tanks associated with
the Inline storage system pump station. Demolish
both tanks, install new discharge piping routed,
install new fiberglass reinforced plastic tank
dome covers, construct reinforced concrete wall,
install adhesive anchor bolted connections of
each tank.
|
|
| Owner Solicitation Name: | US Highway 45 Utility Improvements
|
| Owner Name: | Antigo, City of
|
| Enginner Name: | MSA Professional Services, Inc.
|
| Plankeeper Name |
|
| Scope: | 155 LF 15 PVC Sanitary Sewer, 190 LF 10 PVC
Sanitary Sewer, 85 LF 8 PVC Sanitary Sewer, 170
LF 6 PVC Sanitary Lateral, 680 LF 12 DIP Class
350 Watermain, 82 LF 8 DI Class 350 Watermain,
160 LF 6 DI Class 350 Watermain, 5 EA Fire
Hydrant, 85 LF 1 Copper Water Service, 3 EA
Reconnect Water Service, 100 LF Temporary Storm
Sewer, 3,200 SY 11 Crushed Aggregate Base
Course, 3,200 SY 2 Asphaltic Concrete Pavement,
500 LF Asphaltic Curb, 2,500 LF Sawcut Asphalt
Pavement, LS Traffic Control for Highway.
|
|
| Owner Solicitation Name: | 2004 Chip Sealing
|
| Owner Name: | Fitchburg, City of
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | 38,225 SY of chip seal.
|
|
| Owner Solicitation Name: | 2004 Slurry Sealing Program
|
| Owner Name: | Fitchburg, City of
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | 54,574 SY of slurry seal.
|
|
| Owner Solicitation Name: | West Clayton Road Sanitary Sewer Improvements
|
| Owner Name: | Fitchburg, City of
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Open cut 1,189 LF of 8" PVC sanitary sewer,
sanitary laterals, ditch grading, street and
driveway removal and restoration, and green area
restoration. Alternate to bore in 3 locations
totaling 84 LF of 4" PVC laterals.
|
|
| Owner Solicitation Name: | 2004 Street Improvements
|
| Owner Name: | Fitchburg, City of
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | 74,500 SF of street resurfacing.
|
|
| Owner Solicitation Name: | Landscape Services
|
| Owner Name: | Milwaukee County Dept. of Public Works, Division of Architectural Engineering & Environmental Services
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Landscape services, asphalt paving, tennis court
repair.
|
|
| Owner Solicitation Name: | Asbestos Remediation Zoological Gardens
|
| Owner Name: | Milwaukee County Dept. of Public Works, Division of Architectural Engineering & Environmental Services
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Asbestos remediation.
|
|
| Owner Solicitation Name: | Truck, Cab Forward, Cube Van 0ver 9,600 Pound GVW
|
| Owner Name: | Milwaukee Procurement Services Section
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Truck, Cab Forward, Cube Van 0ver 9,600 Pound GVW.
|
|
| Owner Solicitation Name: | Microbial Sciences Building Existing E.B. Fred Hall Demolition
|
| Owner Name: | Wisconsin Dept. of Administration, Division of Facilities Development
|
| Enginner Name: | State Division's Plan Distribution Unit
|
| Plankeeper Name |
|
| Scope: | Asbestos abatement in and demolition of E.B. Fred
Hall, including the second and third floors and
mechanical penthouse constructed above the
adjacent electrical substation that is to remain.
E.B. Fred Hall is a utility intensive
instructional and research laboratory building of
77,700 gross SF consisting of basement; five
stories above ground and a 2 floor penthouse for
mechanical and elevator equipment. The main
building utilizes a cast-in-place concrete
structure with an envelope of brick veneer on
concrete block, stone window sills, aluminum-
framed window and entrances and built-up roofing
draining internally. The construction of the
6,630 SF per floor substation, office and
laboratory addition is similar to the main
building except for post-tensioned concrete floor
slabs .
|
|
| Owner Solicitation Name: | Well #2 Well Drilling
|
| Owner Name: | Town of Algoma Sanitary Dist. 1
|
| Enginner Name: | Strand Associates, Inc.
|
| Plankeeper Name |
|
| Scope: | Construction of a deep sandstone well to an
estimated depth of 655 LF with 12" casing to a
depth of 275 LF with grout. Final desired pumping
capacity of well is 500 gpm.
|
|
| Owner Solicitation Name: | Can Crusher Installation
|
| Owner Name: | Brown County, Purchasing Dept.
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Install one TeeMark Corp. Super 6 PJ-VC can
crusher. This unit is 115/230v 1 phase, (2 lines
required) process ½ pint to 6-gallong pails.
Blower moves up to 500cfm. 30,000 pounds ram
force, 20 second cycle time. Requires 5cfm @
80psi of air. Features a 35 high stand. Shipping
weight 1800 pounds.
Requirements: 1 air line, isolation valves and
exterior insulation, all electrical work required
including 30 AMP explosion proof disconnect and
heat trace to be controlled by 40 degree
thermostat, new ductwork to be connected to
existing exhaust duct.
|
|
| Owner Solicitation Name: | CTH B Circuit Addition and Facility Upgrade
|
| Owner Name: | Stoughton, City of
|
| Enginner Name: | Strand Associates, Inc.
|
| Plankeeper Name |
|
| Scope: | Circuit addition and facility uUpgrade.
|
|
| Owner Solicitation Name: | Addition and Facility Upgrade
|
| Owner Name: | Stoughton, City of
|
| Enginner Name: | Strand Associates, Inc.
|
| Plankeeper Name |
|
| Scope: | Addition of a new 3 phase distribution circuit as
well as the replacement of the poles of an
existing circuit. The new circuit will be
approximately 1.3 miles along the existing CTH B
corridor.
|
|
| Owner Solicitation Name: | Water Main Relays
|
| Owner Name: | Milwaukee Public Works Dept.
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Furnish and install approximately 4,098 LF of
16", 8", and 6" DIP.
|
|
| Owner Solicitation Name: | Water Street Reconstruction
|
| Owner Name: | Princeton, City of
|
| Enginner Name: | Kunkel Engineering Group
|
| Plankeeper Name |
|
| Scope: | 1 LS unclassified excavation, 1,550 LF 8"
sanitary sewer, 1,810 LF 8" watermain, 2,400 LF
12" through 30" storm sewer, 3,650 LF 30"
concrete curb and gutter, 9,500 SY asphalt
pavement (Including aggregate base courses),
28,000 SF concrete sidewalk, 1 LS street
lighting.
|
|
| Owner Solicitation Name: | Water Main and Sewer Additions, Phase I
|
| Owner Name: | Town of Algoma Sanitary Dist. 1
|
| Enginner Name: | Strand Associates, Inc.
|
| Plankeeper Name |
|
| Scope: | Construction of 10,000 LF of 6" to 12" Class 52
DIP water main and 7,050 LF of 8" SDR35 PVC
sanitary sewer, water services, sewer laterals,
mole 10 water services, and associated
appurtenances.
|
|
| Owner Solicitation Name: | Marquette University Campus Identify and Beautification
|
| Owner Name: | Milwaukee Public Works Dept.
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Grading, irrigation, planting.
|
|
| Owner Solicitation Name: | Trees
|
| Owner Name: | Kenosha Finance Dept.
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | Trees.
|
|
| Owner Solicitation Name: | Downtown Comprehensive Plan
|
| Owner Name: | Madison Purchasing Services
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | The effort will focus on developing general
recommendations for the future physical character
and land uses of downtown Madison. It will
involve an extensive review of existing plans,
studies, and ordinances to identify geographic
gaps and urban design deficiencies. It will also
involve the facilitation of a short but intensive
public involvement process. The final product of
this effort will be a report that will inform the
Comprehensive Plan process and will be utilized
in preparing the downtown portion of that Plan.
|
|
| Owner Solicitation Name: | Ditch Relocation and Wetland Mitigation
|
| Owner Name: | Whitewater, City of
|
| Enginner Name: | Strand Associates, Inc.
|
| Plankeeper Name |
|
| Scope: | Filling approximately 1,400 LF of drainage ditch,
creating approximately 1,400 LF of new drainage
ditch, creating approximately four acres of
wetland, restoration, and related miscellaneous
work.
|
|
| Owner Solicitation Name: | Cable, Communications
|
| Owner Name: | Milwaukee Procurement Services Section
|
| Enginner Name: |
|
| Plankeeper Name |
|
| Scope: | 6,000 LF cable, communications.
|
|
| Owner Solicitation Name: | Hendrickson Center Recreation Facility
|
| Owner Name: | Waupaca, City of
|
| Enginner Name: | Strand Associates, Inc.
|
| Plankeeper Name |
|
| Scope: | Remodeling of approximately 31,000 SF existing
Center facility including new finishes,
electrical, HVAC, and plumbing. Also includes a
new 11,000 SF gymnasium, locker rooms, and lobby
area additions. Existing drives and
parking areas will be revised. A new parking lot
at the lower area adjacent to the building is
included.
|
|